Maryland · Electric & Grid Utilities
Maryland imports 40% of its power — and the capacity to cover the gap just got roughly eight times more expensive.
Maryland leans on imported electricity more than almost any state, so when PJM's capacity market spikes, it lands hard on Baltimore, Washington-suburb, and Eastern Shore bills. Data centers are pulling in new transmission, offshore wind is stalled, and Annapolis is rewriting the rules with the Next Generation Energy Act. Each of those forces reorders the projects on your list. Invizion helps electric utilities re-sequence a capital portfolio in a click — and defend every decision.
The Maryland Landscape
Four forces are moving your project list at once
None of these is theoretical, and none of them waits for your next budget cycle. Together they mean the capital plan you approved last year may already be the wrong plan.
Demand — Load Growth
Data centers are pulling in new wires
PJM ordered the 70-mile, 500 kV Maryland Piedmont Reliability Project — a roughly $424 million line across Baltimore, Carroll, and Frederick counties — largely to serve surging data-center and AI demand.4
Across PJM, tightening supply and demand drove the region's first-ever failure to procure 100% of the capacity it needs, and interconnection delays alone are projected to cost consumers billions.3 Every large new customer is a capacity commitment competing for the same capital.
Reliability — Capacity & Imports
Import dependence meets a scarcity market
Maryland generates only about 35 million MWh but consumes roughly 59 million MWh — importing on the order of 40% of its electricity.1 That leaves the state exposed when PJM's capacity market signals scarcity.
In the 2025/2026 auction the BGE zone cleared at $466.35/MW-day — above the $269.92 RTO-wide record and up from $28.92 the year before — as PJM's reserve margin slipped to 18.5%.2 RTO-wide, total capacity costs climbed roughly eightfold to more than $16 billion.3
Generation — The Transition
Nuclear anchor, stalled wind, a new state playbook
Calvert Cliffs — Maryland's only nuclear plant, at 1,718 MW across two reactors — is the backbone of in-state carbon-free generation, operated by Baltimore-based Constellation.5 Offshore wind was meant to add gigawatts, but US Wind's roughly 1,056 MW off Ocean City still needs remaining state permits, and Ørsted's 966 MW Skipjack project was repositioned after its offtake was terminated.78
The 2025 Next Generation Energy Act now pushes new nuclear and dispatchable generation while reshaping cost recovery — changing what utilities can build and bill for.6
Capital — Transmission
A contested line, a long approval clock
The Maryland Piedmont Reliability Project would run 500 kV across three counties at a roughly $424 million contract value, but it faces fierce opposition — more than 10,000 residents organized against it, all three affected counties passed opposing resolutions, and the Office of People's Counsel argues the state needs no new transmission to meet demand through 2042.4
With no PSC decision expected before early 2027, the timing risk sits squarely on the capital plan. New obligations don't replace the backlog — they stack on it, and something has to move.
Who Runs Maryland's Grid
Exelon-owned investor utilities, FirstEnergy in the west, and member-owned coops
Maryland's distribution grid is carried mostly by three Exelon utilities and FirstEnergy's Potomac Edison, all regulated by the Public Service Commission, alongside large electric cooperatives governed by their members. The pressures are shared; the accountability path differs.
Investor-owned utilities
Rates & capital recovery regulated by the Maryland PSC
Baltimore-based Constellation Energy operates Calvert Cliffs and is signing power deals with data-center operators — a reminder that Maryland's generation and load stories are converging.12
Cooperatives & public power
Governed by members & boards, not PSC rate cases
Coops and munis face the same PJM capacity costs as the IOUs, but recover them through boards and members rather than a PSC rate case.
Rate-Setting & Oversight
Every capital dollar has to be defensible
Whether you answer to the Public Service Commission or a member board, the question is the same: why this project, why now, why at this cost?
- Maryland Public Service Commission (PSC) regulates rates, capital cost recovery, and resource planning for BGE, Pepco, Delmarva Power, and Potomac Edison.15
- Next Generation Energy Act (SB 937, 2025) — signed May 20, 2025 — directs the state to pursue new nuclear generation, opens the door to new dispatchable capacity, and reworks cost recovery and ratepayer protections as bills climb.6
- The Maryland Piedmont Reliability Project is before the PSC — a ~$424 million PSEG line with no decision expected before early 2027, opposed by the Office of People's Counsel, which contends no new transmission is needed through 2042.4
- PJM capacity costs are flowing onto Maryland bills — the BGE zone cleared at $466.35/MW-day for 2025/2026, part of a region-wide surge to more than $16 billion, sharpening scrutiny of every rate request.23
Capital On The Table
The money is moving — can your plan absorb it?
Maryland's grid capital is being pulled in several directions at once — offshore generation, contested transmission, and new state financing. The constraint is readiness: which projects are shovel-ready, which qualify, and how the timing lines up.
- Offshore wind: US Wind's roughly 1,056 MW off Ocean City won federal approval in 2024 but still awaits remaining state permits; Ørsted's 966 MW Skipjack was repositioned after its offtake ended — billions in planned generation now uncertain.78
- The POWER Act (2023) restructured Maryland's offshore wind procurement and directed the PSC to have PJM study transmission upgrades to carry it — shaping where future grid capital lands.16
- Transmission build-out: the ~$424 million Maryland Piedmont Reliability Project is the near-term flashpoint, but PJM's queue and reliability needs point to more transmission capital ahead.4
- State financing & federal credits: the Next Generation Energy Act channels ratepayer relief through the state's energy fund, while IRA elective-pay tax credits put utility-scale solar and storage in closer reach for member-owned coops like SMECO and Choptank.613
Where Invizion Fits
Turn Maryland's grid build-out into a defensible capital plan
Invizion is scenario-based capital portfolio optimization built for utilities. When load forecasts jump, a grant lands, or a retirement date moves, you don't re-plan by hand for weeks — you model it and decide with a record to stand behind.
Model the “what-if” before it's forced on you
A data-center interconnect, a delayed transmission line, a moved retirement date — build the scenario and see the impact on the whole portfolio, side by side with today's plan.
Re-sequence 500 projects in a click
When priorities move, Invizion re-orders the portfolio automatically — accelerating, stretching, or deferring projects against the constraints you set, not weeks of spreadsheet surgery.
Give regulators or your board a defensible record
Every prioritization and trade-off is captured. When you're asked “why this project, why now,” the answer is documented — not reconstructed after the fact.
Maryland's Grid, In Brief
Questions Maryland utility leaders are asking
Short, sourced answers — the same facts we dig into with utilities looking at their capital programs.
Why are Maryland electric bills rising so fast?
What is the Next Generation Energy Act?
What is the Maryland Piedmont Reliability Project?
What's happening with Maryland offshore wind?
Who regulates Maryland's electric utilities?
How does Invizion help Maryland electric utilities plan capital?
Go Deeper
Related from Invizion
Explore Further
See how utilities keep capital plans defensible
Invizion helps utilities model, optimize, and defend their capital programs. Explore how it works, or read our latest thinking on capital planning across the utility sector.
Explore InvizionThis briefing was last reviewed September 2026.
Sources
- U.S. Energy Information Administration — Maryland Electricity Profile 2024: net generation ~35.4M MWh vs. retail sales ~59.0M MWh; nuclear the leading in-state source; 15.04¢/kWh average price. www.eia.gov
- PJM Inside Lines — 2025/2026 Base Residual Auction: $269.92/MW-day RTO-wide (from $28.92), BGE zone $466.35/MW-day, 18.5% reserve margin, 2024. insidelines.pjm.com
- PJM Interconnection (Wikipedia) — capacity costs above $16 billion vs. $2.2 billion prior (~8×); first-ever shortfall in procuring 100% of needed capacity; interconnection-delay costs. en.wikipedia.org
- Maryland Piedmont Reliability Project (Wikipedia) — PSEG, 70 miles, 500 kV, $424M contract, Baltimore/Carroll/Frederick counties, PJM-ordered for data-center demand, opposition, PSC review, no decision before early 2027. en.wikipedia.org
- Calvert Cliffs Nuclear Power Plant (Wikipedia) — 1,718 MW, two reactors, Maryland's only nuclear plant, operated by Constellation. en.wikipedia.org
- Maryland General Assembly — SB 937, Next Generation Energy Act (2025), approved May 20, 2025 (Ch. 625): new nuclear, dispatchable generation, cost recovery and ratepayer provisions. mgaleg.maryland.gov
- US Wind (Wikipedia) — MarWin (248 MW) + Momentum Wind (808.5 MW) = 1,056.5 MW off Ocean City; BOEM approval Sept 2024; onshore work pending state permits. en.wikipedia.org
- Skipjack Wind Farm (Wikipedia) — Ørsted, 966 MW serving Maryland; repositioned/paused after offtake terminated. en.wikipedia.org
- Exelon Corporation — utility customer counts: BGE 1.3M+, Pepco 965,500+ (MD & DC), Delmarva Power 561,500 (DE & eastern MD) electric customers. www.exeloncorp.com
- Baltimore Gas and Electric (Wikipedia) — serves Baltimore City and six central Maryland counties; subsidiary of Exelon. en.wikipedia.org
- Potomac Edison (Wikipedia) — serves western and central Maryland; a FirstEnergy operating company. en.wikipedia.org
- Constellation Energy (Wikipedia) — Baltimore-headquartered; operates Calvert Cliffs; power-supply deals with data-center operators. en.wikipedia.org
- Southern Maryland Electric Cooperative (Wikipedia) — ~161,000 customers across Calvert, Charles, Prince George's, and St. Mary's counties. en.wikipedia.org
- Choptank Electric Cooperative (Wikipedia) — 52,000+ members across nine Eastern Shore counties. en.wikipedia.org
- Maryland Public Service Commission — regulates rates, cost recovery, and resource planning for the state's investor-owned electric utilities. www.psc.state.md.us
- Maryland General Assembly — SB 781, Promoting Offshore Wind Energy Resources (POWER) Act (2023, Ch. 95): offshore wind procurement and PJM transmission analysis. mgaleg.maryland.gov
