South Carolina · Electric & Grid Utilities

South Carolina is building $5 billion of new gas while still paying for a reactor that never ran.

Gigawatt-scale data centers and new manufacturing are stacking load onto a grid that is retiring coal, restarting V.C. Summer, and carrying billions in stranded nuclear debt. Every one of those forces reshuffles the projects on your list. Invizion helps electric utilities re-sequence a capital portfolio in a click — and defend every decision.

The bottom line: South Carolina is committing more than $8 billion to new gas generation and weighing a V.C. Summer nuclear restart while gigawatt data centers arrive and billions in stranded nuclear debt still sit on customer bills. The utilities that keep the lights on will be the ones whose capital plans can re-sequence as fast as the load forecast changes.
1,000 MW1
Load of a single proposed data center in Colleton County — a $6 billion campus five times the size of SC's largest existing centers.
$5B2
Estimated cost of the 2,200 MW Canadys gas plant, a Dominion–Santee Cooper joint venture.
$9B3
Spent on the V.C. Summer reactors that never generated a kilowatt-hour — debt still on customer bills.
$332M4
Dominion Energy South Carolina's requested annual revenue increase in its 2026 rate case.

The South Carolina Landscape

Four forces are moving your project list at once

None of these is theoretical, and none waits for your next budget cycle. Together they mean the capital plan you approved last year may already be the wrong plan.

Demand — Load Growth

Gigawatts of new load, arriving fast

A single proposed data center near Walterboro would draw about 1,000 MW — roughly Santee Cooper's entire share of the planned Canadys gas plant — against existing Google and Meta centers that each use around 200 MW.1

Duke's Carolinas data-center pipeline has swung from more than 100 requests to under five, but if the survivors land it could reach nearly 5,000 MW — about 10% of Duke's output — and Dominion still counts nine potential centers.5 Every large new customer is a capacity commitment competing for the same capital.

Reliability — Adequacy

Nuclear-heavy today, thinner margins tomorrow

Nuclear is South Carolina's single largest source of electricity, and the state generated about 100.5 million MWh in 2024 on roughly 24,700 MW of summer capacity.6

But coal is retiring and load is climbing at the same time, so the reliability margin now depends on new gas and nuclear projects landing on schedule — which is exactly why utilities are committing billions to Canadys and other builds.2

Generation — The Transition

Coal out, gas and nuclear back in

The 2025 Energy Security Act (H.3309) cleared the way for new gas and faster siting.7 Dominion and Santee Cooper are building the 2,200 MW, ~$5 billion Canadys plant with a $431 million pipeline, and Duke is proposing a 1,400 MW, $3.2 billion plant near Anderson targeted for 2031.2

Santee Cooper is retiring the Winyah coal plant within the decade and converting Georgetown to gas.8 Meanwhile the abandoned V.C. Summer reactors may restart under a Brookfield deal, with Santee Cooper keeping up to 25% ownership.9

Capital — Grid & Legacy Debt

Fund the build-out while the old debt is still on the books

Utilities are financing new plants and the transmission to connect gigawatt loads at the same moment they carry the V.C. Summer legacy — about $9 billion spent on reactors that never ran.3

Dominion is asking regulators for a $332 million revenue increase at a 10.5% ROE, and Santee Cooper has authorized up to $700 million in new debt for gas projects.48 New obligations don't replace the backlog. They stack on top of it, and something on the list has to move.

Who Runs South Carolina's Grid

Two big IOUs, a state-owned utility, and a large co-op system

South Carolina's grid is carried by PSC-regulated investor-owned utilities, the state-owned Santee Cooper, and the electric cooperatives that buy through Central. The pressures are shared; the accountability path differs.

Investor-owned utilities

Rates & capital recovery regulated by the SC PSC

Dominion Energy South Carolina ~820,000 electric customers · Midlands & Lowcountry4
Duke Energy Carolinas Upstate SC · Oconee & Catawba nuclear10
Duke Energy Progress Pee Dee SC · part of Duke's nuclear-heavy Carolinas fleet10

Dominion (formerly SCE&G) became a Dominion Energy company after Dominion acquired SCANA in 2018 for $14.6 billion in the wake of V.C. Summer.11

Public power & cooperatives

State-owned board & member-governed, not PSC rates

Santee Cooper State-owned · 165,000+ direct customers; power for co-ops in 46 counties12
Central Electric Power Cooperative G&T for 19 distribution co-ops · 2M+ South Carolinians13
19 distribution cooperatives Serving ~70% of the state's land mass13

A Brookfield restart deal would pay Santee Cooper $2.7 billion, cutting roughly $2.6 billion of V.C. Summer debt off customer bills.3

Rate-Setting & Oversight

Every capital dollar has to be defensible

Whether you answer to the Public Service Commission or a state board, the question is the same: why this project, why now, why at this cost?

  • The SC Public Service Commission regulates rates, capital recovery, and resource plans for the investor-owned utilities — Dominion Energy South Carolina and Duke — with the Office of Regulatory Staff representing the public interest.4
  • Dominion's 2026 rate case seeks a $332 million annual increase at a 10.5% ROE (up from 9.94%), about $20 more a month for a typical residential customer — approvals are not a formality.4
  • The 2025 Energy Security Act (H.3309), signed in May 2025, forces a six-month permitting decision window, adds annual rate-adjustment mechanisms, and creates a nuclear advisory council — reshaping how capital gets approved.7
  • Santee Cooper is state-owned and sets its own rates through a board, but must still get approval to issue debt — it was cleared for up to $700 million for gas projects in late 2025.8
  • The Base Load Review Act legacy still shapes every filing: the V.C. Summer collapse led Dominion to acquire SCANA for $14.6 billion in 2018, and ratepayers continue to carry the cost.11

Funding On The Table

The money is moving — can your plan absorb it?

South Carolina utilities are committing capital at a scale not seen in a generation. The constraint is readiness: which projects are shovel-ready, how the timing lines up, and how the old debt is retired alongside the new build.

  • $700 million in new Santee Cooper debt (2025) for gas projects — ~$120M toward Canadys, ~$300M to convert Georgetown to gas, and $270M+ for gas expansion.8
  • $2.7 billion from Brookfield under the V.C. Summer restart deal — removing roughly $2.6 billion of stranded nuclear debt from Santee Cooper customer bills, with a decision expected by 2028.9
  • $431 million Kinder Morgan pipeline to supply the Canadys plant — new generation carries its own fuel-infrastructure capital.2
  • $8B+ in new generation alone across the $5B Canadys and $3.2B Duke Anderson plants — before the transmission needed to connect gigawatt-scale load.2
  • IRA elective (direct) pay puts utility-scale solar, storage, and nuclear tax credits in reach for public power and co-ops like Santee Cooper and Central — if projects qualify and land on time.

Where Invizion Fits

Turn South Carolina's grid build-out into a defensible capital plan

Invizion is scenario-based capital portfolio optimization built for utilities. When load forecasts jump, a grant lands, or a retirement date moves, you don't re-plan by hand for weeks — you model it and decide with a record to stand behind.

1

Model the “what-if” before it's forced on you

A data-center interconnect, a delayed transmission line, a moved retirement date — build the scenario and see the impact on the whole portfolio, side by side with today's plan.

2

Re-sequence 500 projects in a click

When priorities move, Invizion re-orders the portfolio automatically — accelerating, stretching, or deferring projects against the constraints you set, not weeks of spreadsheet surgery.

3

Give regulators or your board a defensible record

Every prioritization and trade-off is captured. When you're asked “why this project, why now,” the answer is documented — not reconstructed after the fact.

South Carolina's Grid, In Brief

Questions South Carolina utility leaders are asking

Short, sourced answers — the same facts we dig into with utilities looking at their capital programs.

How fast is South Carolina's electricity demand growing?
A single proposed Colleton County data center would draw about 1,000 MW, and if Duke's Carolinas pipeline lands it could add nearly 5,000 MW — roughly 10% of Duke's output.15
What happened with the V.C. Summer nuclear project?
Construction of two reactors was abandoned in 2017 after about $9 billion was spent and none ever ran; a Brookfield deal could now restart them, paying Santee Cooper $2.7 billion and leaving it up to 25% ownership.39
What is the South Carolina Energy Security Act?
H.3309, signed in May 2025, enables new gas generation (including the Dominion–Santee Cooper Canadys plant), imposes a six-month permitting decision window, and adds rate-adjustment mechanisms.72
Does the Public Service Commission set my rates?
The SC PSC regulates rates and resource plans for investor-owned utilities such as Dominion and Duke; Santee Cooper is state-owned and sets its own rates by board. Dominion is currently seeking a $332 million increase.48
Is South Carolina still a nuclear state?
Yes — nuclear is the state's single largest source of electricity, and the potential V.C. Summer restart would add to a fleet that already includes Oconee, Catawba, V.C. Summer Unit 1, and H.B. Robinson.69
How does Invizion help South Carolina electric utilities plan capital?
Invizion is scenario-based capital portfolio optimization for utilities. It lets you model how a data-center load surge, a new gas plant, a coal retirement, or a nuclear restart reshuffles your whole project list, re-sequence the portfolio automatically, and keep a defensible record of every decision for the PSC or your board.

About the Author

GB

Guy Barlow

President, Invizion

Guy Barlow leads Invizion, a capital lifecycle management platform for water and wastewater utilities. He has spent two decades at the intersection of utility capital programs, funding, and analytics, helping utilities make faster, more defensible capital decisions.

Explore Further

See how utilities keep capital plans defensible

Invizion helps utilities model, optimize, and defend their capital programs. Explore how it works, or read our latest thinking on capital planning across the utility sector.

Explore Invizion

This briefing was last reviewed September 2026.

Sources

  1. SC Daily Gazette — Gigawatt (1,000 MW) Colleton County data-center proposal; $6B campus; Google and Meta centers ~200 MW each; Santee Cooper's 1,100 MW Canadys share, Dec 2025. scdailygazette.com
  2. SC Daily Gazette — Canadys 2,200 MW, ~$5B (Dominion–Santee Cooper) plus $431M Kinder Morgan pipeline; Duke Anderson 1,400 MW, $3.2B, online ~2031, Jan 2026. scdailygazette.com
  3. SC Daily Gazette — Brookfield to pay Santee Cooper $2.7B in V.C. Summer restart; ~$9B spent on reactors that never ran; up to 25% ownership, Dec 8 2025. scdailygazette.com
  4. SC Daily Gazette — Dominion Energy South Carolina 2026 rate case: $332M increase, 10.5% ROE (up from 9.94%), ~$20/mo, 820,000 customers, Jan 2026. scdailygazette.com
  5. SC Daily Gazette — Data-center proposals declining; Duke backlog from 100+ to under 5; 470 MW current load; potential ~5,000 MW (10%); Dominion nine potential centers, Mar 2026. scdailygazette.com
  6. U.S. Energy Information Administration — South Carolina electricity profile: nuclear primary source; 100,485,416 MWh net generation and 24,706 MW summer capacity in 2024; 10.90 cents/kWh. eia.gov
  7. South Carolina General Assembly — H.3309, the Energy Security Act (Act No. 41), signed May 12 2025: Canadys joint venture, six-month permitting window, rate-adjustment mechanisms, nuclear advisory council. scstatehouse.gov
  8. SC Daily Gazette — Santee Cooper approved for up to $700M in debt for gas projects (~$120M Canadys, ~$300M Georgetown conversion, $270M+ expansion); Winyah coal retirement within a decade, Dec 3 2025. scdailygazette.com
  9. SC Daily Gazette — V.C. Summer restart prep underway; Brookfield decision expected by H1 2028; ~$2.6B debt to be removed, ~$1B remaining; Santee Cooper up to 25% ownership, Apr 2026. scdailygazette.com
  10. Duke Energy — Duke Energy Carolinas and Duke Energy Progress serve North and South Carolina; about half of Carolinas generation is nuclear (Oconee, Catawba). en.wikipedia.org
  11. Virgil C. Summer Nuclear Station (via Wikipedia) — Units 2 & 3 abandoned July 31 2017; original ~$9.8B estimate; Dominion acquired SCANA in 2018 for $14.6 billion. en.wikipedia.org
  12. Santee Cooper (via Wikipedia) — South Carolina's state-owned electric utility; 165,000+ direct customers; power for co-ops across 46 counties; Cross/Winyah coal, Rainey gas, 800 MW renewables. en.wikipedia.org
  13. Central Electric Power Cooperative — wholesale G&T for South Carolina's 19 distribution cooperatives; 2M+ South Carolinians; ~70% of the state's land mass across all 46 counties. cepci.org